9th May– 15th May 2011 | I’m starting on next Monday onward, to give these 2 days a slacking break. As what we had mentioned, next wed (11th may 2011) script should be 50% done, so I am making to finish it by the deadline, sun (15th may 2011). This include the storyboard have to done by that. So that we could do a discussion with our advisor, Jose, on the next 2 meeting, wed (18th may 2011) |
18th May 2011 (Wed) | Storyboard discussion with our advisor, Jose + the film name |
22th May 2011 (Sun) | Storyboard has to be finalized by that. |
25th May 2011 (wed) | Final discussion about the “Introduction trailer” which include, · Storyline · Character · Location · Equipments · Make-up, clothes and colour treatment that we want · Time-line for production & post-production *we need to discuss about the time-line for this, so that I can include these factor on the final time-line sheet (which what you are reading now) |
26th May 2011 – 4th June 2011 | Finalize the character Mid-discussion about logo design &Ads purpose (wed, 1st June 2011) Start on an audition for promotional trailer and the film |
7th June 2011 – 14TH June 2011 | In between this period, talents have to be finalize and start working out with them with the schedule. *remember to get his/her contact number, would they able to commit their time. Script should be given to them for memorize purpose Credit roll: It would credit to them. 8th June 2011: logo design have to be done by now |
End June 2011 - July 2011 period | Production start *We should have a discussion during meeting about this beforehand As I don’t have any idea how to fix in the time |
August 2011 period | Post-production & “Promotional trailer” start We have to do up a “promotional trailer” by that |